Since January 1, 2026 the 2025 edition of CALGreen has been in force, and
it requires covered projects to recycle or salvage a minimum of 65% of nonhazardous
construction and demolition waste — Section 5.408.1 for nonresidential work
and Section 4.408.1 for residential — or meet a local C&D ordinance,
whichever is more stringent.
You already know that. The problem is never the percentage, it is the paperwork: your
building department will not release a certificate of occupancy, and in several Inland
Empire cities will not release a five-figure refundable deposit, until somebody hands them
certified weight tickets and a facility diversion report. That somebody is your hauler.
What we send
Certified scale tickets from the receiving facility for every load, with
the project address and your job number on them — not a summary we typed up.
Facility diversion documentation naming the receiving facility, so your
plan checker can apply the diversion rate their jurisdiction publishes for that facility.
Tonnage broken out by material and by disposition — recycled,
reused, salvaged, landfilled — reported in weight throughout, because CALGreen
requires the calculation be by weight or volume but never a mix of both.
Two details that get deposits denied
City of origin. Rancho Cucamonga refuses a deposit refund outright if
the weight tickets do not list Rancho Cucamonga as the city of origin, or if they did not
come from the authorized collector or the facility named in the plan.
The clock. Rancho Cucamonga gives you 60 days from final inspection.
Norco forfeits the entire deposit — up to $30,000 — if the final report is
more than 30 days late. We file to your deadline, not ours.
The bin-size trap
San Bernardino County's own published table credits C&D placed in a small
1.5 to 6 cubic yard trash bin at 0% diversion — that material goes
straight to the landfill and none of it counts for you.
The identical debris in a 10 to 40 yard roll-off routed to a mixed-C&D
MRF is credited at 60% to 79% depending on the facility. Putting
construction debris in the building's regular trash bin is the single most common way a
project quietly fails its diversion requirement.
Diversion requirements in the cities we serve.
Local rules override CALGreen when they are stricter, and they vary far more than most
contractors expect. Verify against your own permit conditions — ordinances change and
this table is a starting point, not legal advice.
| Jurisdiction | Diversion required | Plan approved before permit? | Refundable deposit |
| Corona | 65% (CALGreen) | No separate city ordinance located | None found |
| Riverside (city) | 65% by weight | Yes — Form 1 before permit, Form 2 before C of O | Not stated |
| Riverside County | 65% by weight | Yes — Form B before permit, Form C before final | Not stated |
| Norco | 100% inert + 65% other | Yes — no permit until the initial report is approved | 0.75% of cost (1.5% demo), $30,000 cap |
| Jurupa Valley | 65% | Filed through Green Halo after permit number issues | Yes — amount set by the city |
| Chino Hills | 65% | Yes — permits withheld until the plan is approved | If collected, released on approval |
| Chino | 70% | Form CD-1 / CD-2 | Not stated |
| Ontario | 65% | Yes — no demolition or building permit without approval | Not stated |
| Moreno Valley | 50% local, 65% under CALGreen | Yes — approval is a condition precedent to permit | Not stated |
| Lake Elsinore | 50% local, 65% under CALGreen | Yes — reviewed before grading or building permit | 3% of cost or $10,000, whichever is greater |
| Murrieta | 65% by weight | Yes — Part 1 before permit, Part 2 before C of O | Not stated |
| Temecula | 65% by weight | Per TMC 8.36.640 | Not stated |
| Yorba Linda | 65% | Yes — permits withheld until forms are approved | Not stated |
| Perris | Per PMC Ch. 7.44 | Confirm with the city | Confirm with the city |
| Eastvale | 65% (CALGreen) | No separate city ordinance located | None found |
Sources: 2025 CALGreen Sections 4.408 and 5.408 (California Building Standards Commission);
city and county C&D ordinances and permit forms for each jurisdiction listed. Where a
local figure sits below 65%, CALGreen governs on covered projects because the code applies
whichever standard is more stringent.
Where your material actually goes.
Which facility receives the load determines the diversion percentage you get to claim, so
we route deliberately rather than to whatever is closest.
| Facility | City | Stream | Published diversion rate |
| Burrtec West Valley MRF | Fontana | Mixed C&D | 79% |
| Burrtec Agua Mansa MRF | Riverside / Jurupa Valley | Mixed C&D, inerts, wood | 74% |
| CR&R Inland Regional MRF | Perris | Mixed C&D, green waste | 60% |
| Pomona Valley Transfer Station | Pomona | Mixed C&D | 65% |
| Philadelphia Recycling Mine | Jurupa Valley | Clean concrete & asphalt | Inert recycling |
| Maitri Road Recycling | Corona | Inert materials | Inert recycling |
| Greenstone Materials | Perris | Clean concrete & asphalt | Inert recycling |
| Habitat for Humanity ReStore | Riverside, Temecula, Lake Elsinore | Salvage & reuse | Counts as reuse |
Rates as published by San Bernardino County Public Works. Facility rates and permits change
— we confirm the current rate for your specific project before we commit to a number in
your waste management plan.
Clean loads and land clearing
Keep it clean and the math gets easy.
A load of nothing but concrete, asphalt, brick or rock goes to an inert recycler and is
credited far higher than the same material mixed with wood, drywall and trash, which has
to go to a transfer station as mixed waste. Some jurisdictions credit clean inert loads at
100%.
Our 10 yard lowboy includes 10 tons for dirt, concrete, brick, and rock, with a maximum capacity of 10 tons. Keeping these materials separate helps the receiving facility document the load. Confirm the material mix and documentation requirements with the office.
On land clearing, note that CALGreen Section 5.408.3 requires 100% of trees,
stumps, rocks, vegetation and soils from land clearing be reused or recycled on
nonresidential work — not 65%. Green and woody material has to be routed to organics
processing, which is a different facility from your C&D bin.
LEED projects
If you are chasing LEED points.
The LEED v4.1 BD+C credit Construction and Demolition Waste Management is worth
up to 2 points — broadly, one point at 50% diversion and two at 75%. LEED counts
differently from CALGreen in three ways that catch teams out:
- Excavated soil and land-clearing debris are excluded from the LEED calculation — the opposite of CALGreen 5.408.3
- Alternative daily cover counts as waste, not diversion
- Commingled loads must use the receiving facility's average recycling rate, and the certified-facility paths require a Recycling Certification Institute certified facility or approved equivalent
Tell us at the start that the project is pursuing LEED and which path, and we will route
loads and format the reporting to match it. Confirm current thresholds with
USGBC
for your specific rating system.
One thing we will tell you before you ask us to bid. Several cities in the
region — including Rancho Cucamonga, Chino and Fontana — award an exclusive solid
waste franchise, which restricts who may place a roll-off container within city limits. If
your project is in one of those cities, call us and we will tell you honestly whether we can
serve it, refer you if we cannot, and look at whether the inert or clean-load portion can be
handled separately. We would rather lose a bid than get your container red-tagged.